Show upcoming issues doesn't work if the priority field isn't present on the various screens

Issue #178 closed
Devid Verraes created an issue

Steps to reproduce:

  1. Create a task project from the task management template
  2. Remove the priority field from all the screens
  3. Create an issue
  4. Select action : Schedule issue
  5. Create a dynamic due date (don't know if this matters)
  6. Use whatever trigger
  7. Go to the schedule overview and click on the button Show upcoming issue

No issues are shown and a null pointer exception is thrown. It was after a couple of hours trial and error that I found out that is was related to the fact the I didn't have a priority in my screens.

Comments (3)

  1. Łukasz Modzelewski
    • changed status to open

    Hi Devid,

    Thank you for reporting this and your instructions - we reproduced it easily. We are currently working on fix.

    I will let you know when new version is available.

    best regards, Łukasz