Incorrect Start Date
Issue #280
closed
Hello
Today I couldn't add the trigger because the error message was shown "incorrect start date (please see Attachments). I think the Problem is caused by our date Format (please see Attachments).
Is there a way that this can be fixed in The Scheduler?
Many thanks Simona Dill
Comments (3)
-
-
Account Deactivated Hello Lukasz Thank you, it worked with the 2nd Option. Cheers, Simona
-
- changed status to closed
Great :)
- Log in to comment
Hi Simona,
Please take a close look at your: jira.date.time.picker.javascript.format - you have there %p at the end but it is not at "jira.date.time.picker.java.format" - those need to be matching.
You have few options:
remove "PM" from the start/end date - while setting up the trigger (temporary - you would have to always delete it - just test it, now)
remove "%p" from javascript.format (Recommended)
add "a" to java.format (not recommended as you already have 24h format)
Let me know if this works.
Cheers,
Łukasz