Regeneration of sub-tasks

Issue #31 resolved
Lee Allen created an issue

It would be ideal to have an option to regenerate all sub-tasks associated with the original issue when the creation is triggered.

Comments (8)

  1. Marek Cendrowicz

    Hi Lee,

    The Scheduler does not support sub-tasks (creation, updating). We do not have a plan to implement it yet.

    However we have already sub-tasks topic reported in our internal system. I will add your proposal into it too. Could you just give us more details about your imagination - what do you mean saying regenerate all sub-tasks, what should happen then?

    Thanks for contacting,

    Marek Cendrowicz

  2. Lee Allen reporter

    Hi Marek,

    So, for example, I have just setup a scheduled issue that occurs once per month within our team..

    This issue has a number of process steps that I have setup as sub-tasks so that we can see as each part is completed.

    When the scheduled issue is fired to create a new issue for next month the sub-tasks are obviously lost. It would be ideal if The Scheduler could also fire the creation of sub-tasks and associate them with the new issue it has just created.

    Thanks,

    Lee