More Units for Original Estimate on Y-Axis
Issue #63
resolved
Thanks for the plugin!
I have tried to create a new chart with Original Estimate field but it is plotting the Y-axis with seconds. It will be great if it can support more units like days, hours, minutes or even something like quarter days!
Comments (3)
-
repo owner -
repo owner - changed status to resolved
-
reporter It works great, thanks!
- Log in to comment
@PSWai Thank you for the feedback! I decided it would be simplest to let users have control of the Y-axis, and have added an option to scale values as required.
For each dataset there is now a "Y Scaling Factor" option. So, to convert seconds to hours, set it to "3600" and so on.
Jira does something a bit strange where it sets 1d to 8h, so please check your data and let me know if there are any issues, or you need more options in the UI.