Condition to complete sub-tasks and stories before the epic
Issue #739
resolved
I have a epic and some stories under that epic and the stories also have some sub-tasks, the condition that I want to place is until all the sub tasks and stories under the epic are not completed(resolved) the epic cannot be completed(resolved).
Can this be implemented using your add-on
Comments (2)
-
repo owner -
reporter - changed status to resolved
Thanks for the help
- Log in to comment
Hi @Bkappala,
You can do it using "Boolean validator with math, date-time or text-string terms" to transition to Completed status in epic's workflow with the following boolean expression: