Wrong date format with the calendar
Issue #22
resolved
Hello
When i use the plugin versionmanager to manager start and end date of version, i have a strange problem.
The date choose with the calendar haven't the right format :
26/Sep/19
instead
26/sept./19
so i can not update i have to change it.
On the same project, with the same login, and the same calendar but on the Jira version manager (without the plugin) there is not problem, the date select on the calendar is the right and when i update (save), the date is change on the format that the field display (26/06/19) without any message
Comments (3)
-
repo owner -
reporter Thanks, i stop on the 1.1.5 because we are not yet on Jira 8.0, and don’t see that the 1.1.6 is compatible with both 7 and 8.
Problem solve.
-
reporter - changed status to resolved
upgrade to 1.1.6
- Log in to comment
Thanks for getting in contact. This issue is fixed since version 1.1.6 in Version Manager for Jira. Please update. Hope you are on Jira 7.10 or newer.