[TIME-286] Can't do Project Pivot Report for more than 2 months
Issue #286
resolved
One of our users found that Project Pivot Report can't be created for more than two months. He said it was possible in the past. I tried it here and it works. It is some new feature or how can I make it work in our JIRA?
By falta/Jakub Faltýnek on Sun, 30 Sep 2012 23:19:07 -0700
Comments (2)
-
reporter -
reporter Thank you very much!
By falta on Tue, 9 Oct 2012 23:09:10 -0700
- Log in to comment
Yes it is security feature, you just need to add the following property to jira-home/jira-config.properties and restart jira, if you want to set bigger limit, e.g. year:
jira.timesheet.plugin.maxDays = 360
Please see https://studio.plugins.atlassian.com/browse/TIME-169 for reference.
By azhdanov on Sun, 7 Oct 2012 14:15:12 -0700