hi,
is it possible to change the default time for work log? now it is set for one working day = 7.75h If yes, where can i change it? i would prefer to have a blank field.
thanks
Comments (4)
-
-
reporter it looks like it doesn't calculate anything with remaining estimate, just show always for new entry the default number 7.75h (what is the working hours per day in JIRA administration) is it possible to change this number only in the timesheet gadget? because i can't set the working hours per day to NULL in JIRA
-
- changed status to wontfix
Sorry, it's done on purpose, and is selected to let you just start typing to overwrite default value.
-
reporter thanks
- Log in to comment
Hi Peter,
It most likely takes Remaining Estimate, and splits it by days basing on Hours Per Day setting in Administration - Issues - Time Tracking settings.
Thank you.