Day and Month inversed
Hi,
One of our customers is having quite the peculiar issue : on timesheet reports (Project Pivot and Time Sheet reports), the calendar confuses the month with the day.
One picture is worth a thousand words : please have a look at the screenshot attached :
Please also find attached their Date format from Look and Feel and General Configuration.
Here you can see "Today" is set to the 11th of June = 11/06/2018 (they use the d/MM/yyyy format), yet we indeed are the 6th of November (6/11/2018).
So far I have found this error only on those reports (i.e. other datepicker fields are OK). Any help would be greatly appreciated.
Kind regards, Flora (Valiantys)
Comments (4)
-
-
- changed status to duplicate
Duplicate of
#1148. -
Account Deactivated reporter Hi Andriy,
Thank you for your reactivity !
I did not link those two issues. Indeed our customer confirmed the issue seems solved by updating the plugin. (/)Have a good day !
Kind regards, Flora
-
Hi Flora,
Great, thank you for confirmation.
Have a nice day too.
- Log in to comment
Hi Flora,
This is known Jira problem JRASERVER-62857, please see it for possible workaround, i.e. reset date formats to original values.
Also it's fixed in add-on in version 3.2.0 for Jira 7, though.
Thank you.