Andriy Zhdanov created an issue

Forked from issue #295 "[TIME-295] date set in "Project Pivot Report" is not passed into "Time Sheet Report"", reported by Jan Skorepa:

I've discovered another case when this issue appears - but this is not critical for me because our system is not affected. The issue appears if you redefine the "Date/Time Formats" in JIRA (Administration->Look and Feel).

By azhdanov/Andrew Zhdanov on Fri, 26 Oct 2012 01:02:11 -0700

Comments (2)

  1. Andriy Zhdanov reporter

    Committed revision 169845: use DATE_PICKER date formatter

    By azhdanov on Fri, 26 Oct 2012 01:42:56 -0700