Problem running timesheets for 'All Projects'

Issue #492 resolved
Kevin Maughan created an issue

When running a timesheet report, I want to run a combined report of all my projects but I find that selecting All Projects from the project drop down selector finds no time logged. Running each project separately finds the time logged correctly.

Atlassian has removed the temporary files and restarted our instance but the issue is still not resolved.

Comments (3)

  1. Andriy Zhdanov

    Hi Kevin,

    You need to specify Group (e.g. jira-users), or Role (e.g. Users), otherwise Timesheet Report shows time data for currently logged in user only.

    Thank you.

  2. Kevin Maughan reporter

    Thank you for your amazingly fast response. That has fixed my problem.

    Thanks again

    Regards

    Kevin